Question-1: Procurement documents should have all of the following attributes EXCEPT:
a. Flexible enough to allow consideration of seller suggestion
b. Contract statement of Work
c. Describing the desired form of response
d. Including the qualified sellers list
Answer-1: D The qualified sellers list are those sellers who are asked to submit a proposal or quotations. This is the output of 'request seller response' process(Ref: PMBOK).

Question-2: Generally, a Request for Quotation(RFQ) differs from Request for Proposal(RFP) in that the:
a. RFQ is a type of documentation used to request price quotations from prospective sellers of common or standard products
b. RFQ is a type of documentation used to request proposals from prospective sellers of products
c. RFQ is a type of documentation used to request prospective sellers to provide various pieces of information related to seller capability
d. RFQ is a type of documentation used to request proposals from various functional departments within performing organization
Answer-2: (Check below)

Question-3: An authorized contractor administrator from buyer should provide what to the seller that the contract has been completed.
a. A formal written notice
b. Letters of commendation to all project staff
c. Informal notice of acceptance to the contractor
d. Internal notice to senior management/buyer
Answer-3: (Check below)

Question-4: Which type of contract should be used for a well defined product?
a. Unit-price contract
b. Fixed price contract
c. Cost -reimbursable contract
d. Partnership contract
Answer-4:

Question-5: Contract documentation includes all of the following EXCEPT:
a. Seller developed technical documentation
b. Financial documents
c. The RFP or RFQ and seller's proposal
d. Results of contract related inspections
Answer-5:

These PMP EXAM FAQs on procurement management cover questions and answers very useful for the PMP aspirants.

Question-6: Bidder's conferences used to:
a. Plan contracting
b. Perform contract administration
c. Ensure that all prospective sellers have a clear, common understanding of the procurement
d. Select sellers
Answer-6:

Question-7: All of the following need NOT be present to have a contract EXCEPT
a. Detailed specifications
b. Acceptance of both seller and buyer
c. Address of the seller
d. Buyer's signatures
Answer-7:

Question-8: In a fixed price contract, the fee or profit is:
a. Unknown to the buyer
b. Part of the negotiation involved in paying every invoice
c. Applied as a line item to every invoice
d. Determine with the other party at the end of the project
Answer-8:

Question-9: An advantage of a fixed price contract for the buyer is:
a. Cost risk is lower
b. Cost risk is higher
c. There is little risk
d. Risk is shared by all parties
Answer-9:

Question-10: With which type of contract is seller MOST concerned about project scope of work
a. Fixed price
b. Cost reimbursable
c. Time and Material
d. Purchase Order
Answer-10: In a fixed price contract, the seller has the cost risk and therefore wants to completely understand the scope of work from each other.

Answers to Project Procurement Management FAQS

1. D   2. A   3. A   4. B   5. C   6. C   7. B   8. A   9. A   10. A  

Other PMP EXAM FAQs

PMP EXAM FORMULAS➤
PMP EXAM PREP TIPS➤
PMP EXAM FAQs-General Project Management➤
PMP EXAM FAQs-Project Integration Management➤
PMP EXAM FAQs-Project Scope Management➤
PMP EXAM FAQs-Project Time Management➤
PMP EXAM FAQs-Project Cost Management➤
PMP EXAM FAQs-Project Quality Management➤
PMP EXAM FAQs-Project HR Management➤
PMP EXAM FAQs-Project Risk Management➤
PMP EXAM FAQs-Project Communication Management➤
PMP EXAM FAQs-Project Procurement Management➤